Church Building Commitee

Frame Completion

9th June 2021

With the blessings of the Lord Almighty, the Church Building Committee is happy to report that so far, the construction is progressing as scheduled. The trusses, decking and water proofing for the roof are now complete, the soil removal on the back of the lot is done, while electrical and plumbing rough-ins, sprinkler system and windows have been installed. The on-site civil work in the front of the lot is also mostly complete. With that, the Frame of the building is now complete.

Currently, work is being carried out to complete the HVAC system installation, skylights and on-site civil work on the back of the lot. The next steps would be to complete the roof insulation and metal roof, doors, electrical and plumbing systems, and the on-site civil works on the back of the lot, including the parking retaining walls.