Start of Foundation Forming

On 29th January 2021

The Site preparation for ESC (Erosion & Sediment Control) is ongoing and the shoring and excavation for the building has now been completed. The Forming & Framing crew have now started work on the Foundation Forming, and if all goes well, with the Lord's Blessings, the pouring of the foundation will start next week.

The Construction project is so far going as planned (a few days earlier than projected, actually). This is just the start, we need everyone's daily prayers and support to face the financial and logistical challenges ahead of us.